CEB Prototype 1 Fab

From Open Source Ecology

Jump to: navigation, search

Here are most of the details for fabricating CEB Prototype 1.

We start with raw metal. Drill holes in the structure pieces, 7/16" x 6 inch u-channel:

Image:1_cebfab.jpg

Begin putting the frame together:

Image:2_cebfab.jpg

Use 1/2", grade 8 bolts, and the frame is complete:

Image:3_cebfab.jpg

Cut Nylon 6/6 liner to size, and use it for abrasion resistance for the compression chamber:

Image:4_cebfab.jpg

Install the Nylon liner in the compression chamber:

Image:5_cebfab.jpg

Add the plate for the compression chamber box, with the Nylon underneath:

Image:6_cebfab.jpg

Put in spacers for the bottom of the frame, as the 5 inch cylinder that we used was fatter than 6 inches of the frame width:

Image:7_cebfab.jpg

Assemble and stand the machine:

Take out the acetylene torch:

Image:9_cebfab.jpg

And slice up metal pieces for the pressing plate:

Image:10_cebfab.jpg

Grind and prepare pressing plate assembly:

We used a 20 kW tractor power-take-off (PTO) genearator to feed the welder.

Image:16_cebfab.jpg

Here is the prepared pressing plate assembly with cylinder pin:

Image:17_cebfab.jpg

Add the 5 inch, 2.5 inch rod, ~20 ton hydraulic cylinder:

Image:18_cebfab.jpg

Fit the pressing plate assembly on the cylinder:

Image:19_cebfab.jpg

Prepare sides of the compression plate, so the compression plate assembly moves straight vertically:

Here is the finished press plate and cylinder mount before assembly:

Image:23_cebfab.jpg

Here is the assembled press plate, with rubber liner on top:

Image:24_cebfab.jpg

Note how the two pieces are bolted together:

Image:25_cebfab.jpg

Now we fit the compression box assembly in the frame, attach the cylinder and hydraulics, and test motion of the cylinder:

Now we fit the cylinder and press plate into the frame:

Image:29_5_cebfab.jpg

We close up the compression box:

Image:30_cebfab.jpg

Here we show other details of mounting the cylinder in the frame:

Thy cylinder is mounted and the pin holder is ready for welding:

Image:36_cebfab.jpg

Winter came, so we moved operations into the greenhouse:

Image:37_cebfab.jpg

We attached the hopper table to the frame:

Image:38_cebfab.jpg

And we are ready to test the pressing of the first brick:

Image:39_cebfab.jpg

We filled the compression chamber with soil:

Image:40_cebfab.jpg We covered the latch, and fixed it in place (not shown):

Image:41_cebfab.jpg

And we pressed the first brick:

Image:42_cebfab.jpg

Here is the first block ejected:

We show the block and the earth it's made from:

Image:44_cebfab.jpg

Next comes the hopper assembly. Here is the hopper cylinder:

Image:45_cebfab.jpg

Here is the liner for the hopper table:

Image:46_cebfab.jpg

Here is the hopper assembly in the making. Soil enters the compression chamber through the hole in the bottom plate:

Image:47_cebfab.jpg

And here is the finished hopper assembly, ready for testing:

Image:48_cebfab.jpg

We gather a pile of semi-frozen dirt:

Image:48_5_cebfab.jpg

And pack the compression chamber, first manually:

Image:49_cebfab.jpg

Then we fill the hopper. The soil was too wet, but here are some sample bricks:


And that's it for Phase 1. Now we'll be testing the machine and building an improved prototype with an XYZ torch table to facilitate metal preparation.